Wednesday, September 3, 2008

I met with our engineering firm today and they have completed the site work and drawings for Glenknoll Elementary School and Yorba Linda Middle School.  We will need to put these specs and drawings into a bid document.  We met with our purchasing manager and it appears that we can have the bid out next week.

Although we could probably get the bidding done by the end of September, there is only one school board meeting in September and the next board meeting is October 14th  We fully plan to make this date, so the work could begin thereafter.  